1. Excavation - Prepare the excavation by adding 4" - 6" inches to over all length and width of box. The depth should be a minimum of 6" inches deeper than the height of the box.

2. Installation - Level and fill bottom of hole and compact material. Level so that the top of the box will be flush to grade when using material such as gravel, (or recommended materials by agencies). These materials are recommended because of their draining characteristics. Place box in hole.

3. Backfill requirements - Place selected backfill material with rocks no larger than 3/4" inch. Compact either mechanically or by flooding, whichever is in accordance with governing agency. Note: It may be necessary to brace inside of box walls while you are backfilling the hole.

 

Installation can vary by governing agency, design and specification. We warranty our products to be free of defects in material and workmanship, but once it is out of our control, we accept no responsibility or liability for damages.

 

 